Installation Guide

Standard Installation and Commissioning Guide for Automatic Labeling Machine

Document Number: IG-ALM-STD-2026

Effective Date: January 1, 2026

Scope: ALM Series Standard Automatic Labeling Machines

Status: Controlled Release


1.0 Introduction & Safety General Rules

1.1 Purpose of the Document

This document provides professional technicians with a complete, systematic, and safe procedure for installation, commissioning, and acceptance of automatic labeling machines. Strict adherence to this guide is a prerequisite for ensuring design performance, operator safety, and full technical support from the manufacturer.

1.2 Target Audience

  • Field Installation Engineers
  • Equipment Maintenance Technicians
  • Electrical Automation Engineers
  • Production Site Managers

1.3 Safety Level Definitions

  • DANGER: Severe injury or death if ignored.
  • WARNING: Serious injury risk.
  • CAUTION: Equipment damage risk.
  • NOTE: Helpful guidance.

1.4 General Safety Requirements

  1. Perform energy isolation on all sources before work.
  2. Use personal protective equipment (safety shoes, glasses, gloves).
  3. Only trained personnel may operate the equipment.
  4. Do not remove or bypass any safety devices.
  5. Ensure clean, dry, well-lit working environment.

2.0 Pre-Installation Planning & Preparation

2.1 Site Assessment

Ensure sufficient space for equipment layout, power, and air supply accessibility, as well as proper grounding and lighting.

2.2 Utility Preparation

  • Electrical, compressed air, and network connections must be ready.
  • Check tools and assembly equipment before installation.

3.0 Equipment Receiving & Unpacking

Check for shipping damage and verify parts according to the packing list. Use proper lifting equipment when handling heavy modules.


4.0 Mechanical Installation

Assemble the machine frame and modules, tighten all fasteners, and ensure proper leveling. Align conveyor and mounting points to avoid misalignment during operation.


5.0 Electrical & Pneumatic Installation

Connect main power supply, control panel, sensors, and actuators according to the wiring diagram. Install pneumatic lines, filters, regulators, and valves per specifications.

5.1 Vision System

Mount cameras, lenses, and lighting. Connect the vision system to the control network. Perform initial calibration for label alignment and fiducial detection.


6.0 Commissioning & Performance Verification

Perform dry runs, verify mechanical motion, electrical signal integrity, pneumatic function, and vision system accuracy. Adjust speed and label placement parameters.

6.1 Performance Metrics

  • Labeling speed: up to 1500 pcs/h depending on product size.
  • Labeling accuracy: ±0.1 mm–0.2 mm.
  • Yield rate: ≥ 99.5%.

6.2 Process Flow Diagram

Receiving & Unpacking

Mechanical Installation

Electrical & Pneumatic

Vision System

Commissioning & Testing

Operator Training

Acceptance & Handover


7.0 Training & Operator Guidelines

Provide hands-on training for operators, focusing on safe operation, daily maintenance, troubleshooting, and emergency procedures.


8.0 Appendices & Contact Information

8.1 Glossary

ALM – Automatic Labeling Machine

PLC – Programmable Logic Controller

Fiducial – Reference mark for vision alignment

8.2 Manufacturer Contact

ALM Automation

Website: https://automatedlabelingmachine.com

Email: solutions@automatedlabelingmachine.com

Phone: +86 131 1363 4212


End of Document